Tramway Track Repairs Progressing: New Stages and Plans

At the intersection of Prince Volodymyr the Great Avenue and Academician Zabolotny Street, the second stage of tramway track repairs has begun.

The first stage of the medium repair on the tramway track at this intersection has been completed. The work was carried out from May 16 to June 2 and covered a 50-meter straight section.

Currently, the second stage has started, which involves repairing an additional 100 meters of tramway. This stage will last from June 3 to June 26. Following this, two more stages are planned, including a major repair with partial replacement of the curved section.

The total length of the repair section will be 250 meters. The work is being conducted in phases, with partial restrictions on vehicle movement.