L o a d i n g . . .

Restoration of Services at De Nova Data Center

The data center that experienced disruptions affecting banks and other services has now restored most of its operations for clients.

This was reported by De Nova's CEO, Maxim Ageev.

According to him, the power outage at the data center lasted from 8:03 to 8:17. The reasons for the incident are currently unknown, but Ageev dismissed the possibility of a cyberattack.

He explained that planned maintenance was being conducted at the data center when the automatic power switch system malfunctioned, blocking access to backup power.

Ageev noted that De Nova has restored services for most clients, who are now beginning to resume operations, although some companies are still "in line" for restoration, which is expected to happen within a few hours.